The EES requires proportionate and robust investigation of alternate feasible options
Is there a genuine risk that the EES process won't be in AusNets favour?
The Environmental Effects Statement (EES) process is the most rigorous environmental impact assessment process in Victoria. The purpose of the EES is to ensure that major projects are designed, constructed, and operated to avoid, minimise (if avoidance is not possible) or manage adverse impacts on environment and community, in that specific order.
To fulfil the requirements of the EES, rigorous and transparent investigation of potential environmental impacts is essential. The EES should proportionately document the likely environmental effects of feasible alternatives, particularly where these offer a potential to avoid or minimise adverse environmental effects whilst meeting the objectives of the project.
So, what are feasible alternatives?
Route selection should try to avoid, minimise, or offset impacts on important environmental, social, cultural, landscape values and strategic land use conflict by utilising existing rights-of-way as a priority. Replacing overhead HVAC with HVDC on existing infrastructure and deployment of underground HVDC technology should also be considered as a preferred transmission option to avoid community and environmental impacts.
This is the way transmission should be built — in an environmentally responsible manner that respects landowner rights and can be replicated across the country to building the grid of the future.
Proportionate Investigations of Feasible Alternatives
As mentioned in the opening, the EES should proportionately document the likely environmental effects of feasible alternatives, particularly where these offer a potential to avoid or minimise adverse environmental effects whilst meeting the objectives of the project. If all potential corridors or feasible alternatives are not rigorously and proportionally investigated, Energy Grid Alliance is concerned the WVTNP risks failure of the EES process.
In a recent story by ABC News in relation to compensation plans for landowners, AusNet insists it's not a 'done deal' – encouraging landholders to continue discussions with the company. Speaking to Nicole Chvastek on ABC Victoria's Statewide Drive Program, executive project director Stephanie McGregor said technical surveys would continue as AusNet prepares the EES.
"There is a genuine risk in that process that it won't be in our favour," Ms McGregor said.
"We're required to look at both overhead and underground as part of the EES process the compensation process itself is agnostic of the actual physical solution," she said.
How proportionate have the investigations been?
It is encouraging to hear that undergrounding will in fact being investigated as to date, there does not appear to be any evidence to indicate that investigation of alternatives, whether underground HVDC or alternate corridors, has been rigorous or proportionate. As accurate information can only be obtained through detailed field studies, Energy Grid Alliance sought clarification from AusNet Services as to why further detailed assessments were not conducted on the proposed southern corridor, existing easements or an underground HVDC alternative, using existing rights-of-way. There has been no response to this request to date.
Following review of the WVTNP single corridor selection presentation, webinar series and on-on-one discussions it has become apparent that the level of technical investigation conducted by associated specialists on alternate corridors and technical options, such as undergrounding HVDC has not been proportionate.
The following table illustrates an understanding of the level of investigation that was conducted by Tetra Tech Coffey2 on potential corridors within the broader area of interest. The purpose of these desktop investigations was to identify a preferred final corridor.
TABLE 1
Evaluation | Northern Corridor | Southern Corridor | Underground HVDC |
---|---|---|---|
Cultural heritage | Desktop analysis | Desktop analysis | Dismissed |
Biodiversity | Desktop analysis | Desktop analysis | Dismissed |
Landscape and visual | Desktop analysis | Desktop analysis | Dismissed |
Planning and land use | Desktop analysis | Desktop analysis | Dismissed |
Agriculture | Desktop analysis | Desktop analysis | Dismissed |
Length | Desktop analysis | Desktop analysis | Dismissed |
Constructability | Desktop analysis | Desktop analysis | Dismissed |
There is no clear evidence to suggest that proportionate detailed assessment of feasible alternatives has been considered.
The following diagram summarises the outcomes of the investigations listed in Table 1. The key points raised in the presentation were:
- Conflicting or competing land uses and controls are inevitable
- No perfect route
- All routes have ‘pinch points’ with high constraints
- High constraints need to be managed
DIAGRAM 1
It is clear through this evaluation that both the northern and southern corridor options are highly constrained and offer no perfect route. It is important to note that while there is minimal difference in the overall assessment of constraints, the northern corridor was shortlisted as the least-worst solution (preferred corridor) to undergo further detailed investigation to establish a final transmission route.
It is important to note that during the one-on-one webinar discussions with technical specialists it was indicated that:
- The work required to conduct detailed studies on alternate corridors was too great, so the focus has been on the preferred corridor only. (Energy Grid Alliance note that this approach cannot produce an effective and proportionate assessment of the least-impact solution as is required by the EES process. Not conducting rigorous and proportionate assessments because the volume of work is 'too great' will not produce a superior environmental outcome).
- The reason technical field studies are required on the preferred corridor is that a lot of information is not documented, meaning constraints or impacts are not able to be accurately determined through desktop analysis alone and that [we] would be surprised at what has been found to date. (Energy Grid Alliance note that as accurate information can only be obtained through detailed field studies, excluding alternate feasible options from this assessment will not produce an effective and proportionate assessment of the least-impact solution).
According to the EES Scoping Requirements4, where a feasible option provides a distinct opportunity for superior environmental outcomes, this should be investigated and documented in the EES. Detailed assessment of particular alternatives is necessary where alternatives have the potential to deliver suitable social, environmental and economic outcomes.
The following table illustrates an understanding of the level of investigation, that has or is soon to be conducted along the final preferred corridor (least-worst option), compared to alternate corridors, existing easements and underground alternatives. This assessment criteria has been extracted from AusNet Services ‘Environmental and key project approvals’ fact sheet3.
TABLE 2
Evaluation | Preferred Corridor | Dismissed Corridors | Underground HVDC |
---|---|---|---|
Agriculture and farming | Field Studies | No further studies | Dismissed alternative |
Air quality | Field Studies | No further studies | Dismissed alternative |
Aviation and aerial fire-fighting | Field Studies | No further studies | Dismissed alternative |
Biodiversity | Field Studies | No further studies | Dismissed alternative |
Bushfire risk | Field Studies | No further studies | Dismissed alternative |
Electronic interference | Field Studies | No further studies | Dismissed alternative |
Historic heritage | Field Studies | No further studies | Dismissed alternative |
Human health | Field Studies | No further studies | Dismissed alternative |
Landscape and visual | Field Studies | No further studies | Dismissed alternative |
Noise and vibration | Field Studies | No further studies | Dismissed alternative |
Project alternatives | Field Studies | No further studies | Dismissed alternative |
Socioeconomic | Field Studies | No further studies | Dismissed alternative |
Surface water and groundwater | Field Studies | No further studies | Dismissed alternative |
Traffic and transport | Field Studies | No further studies | Dismissed alternative |
Once again, there is no clear evidence to suggest that proportionate detailed assessment of feasible alternatives has been considered.
Requirements of the EES
The following information has been extracted from the EES Scoping Requirements (December 2020) for the purpose of understanding requirements for investigation and assessment of feasible alternatives including underground High Voltage Direct Current (HVDC) transmission as a project alternative.
The primary purpose of the EES process is avoiding environmental impact. Underground HVDC seems to be the technical solution of choice due to the decreased socioeconomic and environmental impact. If not proportionally investigated, AusNet Services should be required to apply the EES process again or risk failure of this process. To date, AusNet Services have not provided evidence that investigation of alternatives, whether underground HVDC or alternate corridors, has been proportionate.
1.2 Minister’s requirements for this EES
In the procedures and requirements, the Minister identified broad key matters and environmental risks that the EES should investigate and document:
- alternative corridors, alignments, site locations, designs or other options for the planning, construction or operation of the project;
3.2 Content and style
The EES should provide a clear, objective and well-integrated analysis of the potential effects of the proposed project, including proposed avoidance, mitigation and management measures, as well as feasible alternatives. Overall, the main report should include:
- responses to issues, including alternative options, raised through public and stakeholder consultation;
3.4 Project alternatives
The EES should document the proponent's design development process leading to the proponent’s preferred form of the project as presented in the EES. The EES should explain the proponent’s criteria for evaluating the feasibility of potential alternatives and explain how specific alternatives were shortlisted or rejected for evaluation within the EES. The EES should document the likely environmental effects of feasible alternatives, particularly where these offer a potential to avoid or minimise adverse environmental effects whilst meeting the objectives of the project.
The referral of the project under the EE Act presented the project in terms of an area of interest rather than a proposed alignment. Alignment selection can be a very important way of avoiding or minimising adverse impacts for linear infrastructure projects. Key aspects of the project, for which the EES will need to demonstrate consideration of feasible alternatives, include:
- the rationale for the preferred mode of construction (overhead or underground, including potential for partial underground construction); and
- other feasible alternatives raised through feedback from the community or other stakeholders
The process for identification and analysis of the project alternatives will need to be documented in the EES including:
- assessment and comparison of the technical feasibility and environmental implications of alternative options considered;
While the assessment of environmental effects of site selection, alignment and design alternatives must address the matters set out in these scoping requirements, the depth of investigation of alternatives should be proportionate to their potential both to minimise potentially significant adverse effects and to meet project objectives. References to “the project area of interest” are to be read as applying iteratively to potential corridors or alignments for the project as they emerge within the project area of interest.
What if a project alternative costs more?
It’s important to remember, with any large-scale linear infrastructure project, there will always be planning scheme, policy and framework conflict. One conflict worth noting is that the RIT-T is not allowed to consider socioeconomic or environmental disbenefits in net benefit calculations. The EES on the other hand is only concerned with superior environmental outcomes and does not consider project costs. Nowhere in any EES documents or Ministerial referrals are project costs mentioned as a factor to be considered.
So when alternatives are dismissed purely based on cost without proportionate investigation, this contravenes the purpose of the EES process.
Risk of genuine failure of the EES process
If feasible options, that deliver superior environmental outcomes, are not proportionately investigated, the proponent risks material project delays while these alternatives are investigated and documented. The alternate outcome is failure of the EES process.
The EES should investigate and document:
- alternative corridors
- alternative alignments
- site locations
- designs or other options for the planning, construction or operation of the project
- alternative options, raised through public and stakeholder consultation
- mode of construction (overhead or underground, including potential for partial underground construction)
- re-stringing existing transmission infrastructure using HVDC
- undergrounding HVDC
Energy Grid Alliance agree with Ms McGregor that there is a genuine risk in the EES process that it won't be in favour of AusNet Services.
These risks will continue to exist until proportionate investigations are carried out on alternative corridors, alignments, site locations, designs or other options for the planning, construction or operation of the project.
The option that delivers superior environmental outcomes is the only acceptable option.
REFERENCES
- WVNTP - High-Level HVDC Alternative Scoping Report https://www.moorabool.vic.gov.au/files/content/public/about-council/large-projects-impacting-moorabool/western-victoria-transmission-network-project/wvtnp-high-level-hvdc-alternative-scoping-report.pdf
- Tetra Tech Coffey - Single Corridor Selection Presentation, 13 July 2021 https://www.westvictnp.com.au/52677/widgets/339677/documents/212981
- Fact Sheet - Environmental and key project approvals https://www.westvictnp.com.au/62122/widgets/312640/documents/207514
- Scoping Requirements Western Victoria Transmission Network Project Environment Effects Statement https://www.planning.vic.gov.au/__data/assets/pdf_file/0020/506504/WVTNP-EES-Scoping-Requirements-final.pdf